PROJECT :
Access Controlled Highway of 4 lane with Paved Shoulders from Design Ch. 89+900 to Design Ch.132+100 in Belgaum – Hungund – Raichur Section of NH748A in State of Karnataka on HAM Under NH(O) (Project Length – 46.200 Kms) (Package-3)
Badami Highways Private Limited (BHPL or the Concessionaire) is a special purpose vehicle company promoted jointly by BEKEM Infra Projects Private Limited (BIPPL) and DHD Infracon Private Limited (DHDIPL) to undertake development, maintenance and management of Access Controlled Highway of 4 lane with Paved Shoulders from Design Ch. 89+900 to Design Ch. 136+100 in Belgaum – Hungund – Raichur Section of NH748A in State of Karnataka on HAM Under NH(O) (Project Length – 46.200 Kms) (Package-3) (hereinafter referred to as the project).
The Project highway comprises section of NH-748A starting at Km.89.100 near Batkurki Village and ending at Km. 136.100 near Guledagudda Village, passing through Shirasapur, Chinchalkatti LT, konkanakappa, and Teggi which fall in Bagalkot & Raichur district, in the State of Karnataka. with approximate design length of 46.200 km.
Project Details
Particulars | Details |
Project Name | Access Controlled Highway of 4 lane with Paved Shoulders from Design Ch. 89+900 to Design Ch.132+100 in Belgaum – Hungund – Raichur Section of NH748A in State of Karnataka on HAM Under NH(O) (Project Length – 46.200 Kms) (Package-3) |
Design length | 46.200 Km |
PPP Mode | Hybrid Annuity Mode |
Concession Authority | National Highways Authority of India |
Concessionaire | M/s Badami Highways Private Limited |
Concession Period | 17 years from Appointed Date including construction period |
Construction period | 2 Years i.e., 730 days |
EPC Contractor | Bekem Infra Projects Private Limited |
Key Dates | |
Bid Due Date | 21St February 2024 |
Bid award date (LOA Date) | 9th March 2024 |
Execution of Concession Agreement | 28th June 2024 |
Financial Closure | 28th November 2024 |
Appointed Date (AD) | 4th April 2025 |
Construction starts date (Envisaged) | 4th April 2025 |
Commercial Operation Date (COD) | 4th April 2027 |
Concession End Date | 4th April 2042 |
Authority | National Highways Authority of India |
Sponsor (EPC Contractor) | M/s. BEKEM Infra Projects Private Limited, # Plot No.289, Avenue-1 Road No.06, Kakatiya Hills, Madhapur, Hyderabad -500081
|
Project Company (Concessionaire) | M/s Badami Highways Private Limited
3rd Floor, Plot No.289, Sarojini Naidu Nagar, Madhapur, Shaikpet, Hyderabad, Telangana, India- 500081 |
Major Scope of the Project:
Description | Unit | Scope |
Road Length | kms | 46.2 |
Major bridge | Nos | 3 |
Minor bridge | Nos | 19 |
ROB | Nos | 1 |
Utility structure | Nos | 1 |
LVUP | Nos | 11 |
VUP | Nos | 4 |
VOP | Nos | – |
Interchange | Nos | – |
Box Culverts | Nos | 143 |
Culverts on crossroads | Nos | 15 |